In the recent past Uhde carried out the basic and detailed engineering for the revamp of two Egyptian urea plants, which have basically the same starting point with a capacity of 1925 MTPD each. The capacities of these plants, which where commissioned by Uhde in the years 2000 and 2006 will be increased by about 17% to a new capacity of 2250 MTPD. Furthermore those two plants mainly differ in their finishing sections since one uses UFT technology for the granulation and the other uses the granulation technology of Stamicarbon.